Nov 17, 2023 | Cases, Milling, News
Case Study: Onshore, Asia +250 ft of Dual-String Section Milling completed with 2-access cuts and 3-milling runs at +9,700 ft! The Dynasty Energy Services Team was approached by a company in need of section milling a challenging well in Asia. Given the depth,...
Jan 23, 2023 | Uncategorized
HOUSTON — January 2023 — Dynasty Energy Services, LLC. announced today that it has entered into an agreement with Helix Energy Solutions Group, Inc. (NYSE: HLX) to develop and market Dynasty’s section milling technology. Dynasty Energy Services, LLC., a global...
Dec 14, 2020 | Cases, Milling
Well Location: Offshore California, USA. Operator Challenge: Operator needed to P&A the well while maintaining all casing strings integrity, pass through the 9 5/8” OD, 43#, 8.755” ID casing then section mill a 25’ window in the 13 3/8” OD, 72#, 12.347” ID casing....